ITS » Undergraduate Theses » Teknik Sipil D4 Posted by tondoindra@gmail.com at 25/11/2015 11:24:03 • 1121 Views
ANALISIS PEMILIHAN METODE PEMASANGAN
GELAGAR JEMBATAN DITINJAU DARI SEGI BIAYA
DAN WAKTU PADA PEMBANGUNAN JEMBATAN
BUNGUR KECAMATAN MUNJUNGAN TRENGGALEK
ANALYSIS METHOD BASED ON FITTING BRIDGE
GIRDER ASPECTS OF DEVELOPMENT COSTS AND
TIME BRIDGE BUNGUR DISTRICT MUNJUNGAN
TRENGGALEK
Author : SUGIANTO ( 3113040502 )
ABSTRAK
Salah satu bagian dari pembangunan dan
pengembangan transportasi adalah pembangunan jembatan.
Jembatan Bungur terletak di Desa Bungur Kecamatan
Munjungan Kabupaten Trenggalek. Jembatan ini didesain
dengan menggunakan struktur jembatan komposit. Panjang
jembatan ini 84 meter dengan lebar 7 meter dilengkapi trotoar di
kiri dan kanan jembatan. Jembatan ini terdiri dari 6 span. 2 span
dengan bentang 12 meter dan 4 span dengan bentang 15 meter.
Gelagar yang digunakan adalah baja WF 700. 300.
Metode yang telah dilaksanakan adalah metode
excavator sedangkan yang digunakan sebagai pembanding
adalah metode peluncuran manual. Selain itu juga dihitung
berapa waktu pelaksanaan dan jumlah biaya yang dibutuhkan
untuk menyelesaikan bangunan atas jembatan Bungur.
Dari hasil analisa dan perbandingan terhadap kedua
metode tersebut sesuai dengan parameter-parameter penguji
yang ada didapatkan kesimpulan bahwa untuk menyelesaikan
bangunan atas jembatan bungur dengan metode excavator
diperlukan waktu 121 hari dengan biaya Rp 3.287.286.91919.
Sedangkan dengan metode peluncuran manual diperlukan waktu
139 hari dengan biaya Rp 3.228.751.74917.
ABSTRACT
One part of the development and transport development is
the construction of the bridge. The bridge is located in the village
of Bungur Munjungan sub District District of Trenggalek. The
bridge was designed by using a composite bridge structure. The
length of the bridge is 84 meters with a width of 7 meters
equipped with sidewalks on either side of the bridge. The bridge
consists of 6 span. 2 span with a span of 12 meters and 4 span to
span 15 meters. Used is a steel girder WF 700. 300.
The method has been implemented is the method of
excavators while the comparator is used as the launch of the
manual method. Moreover it also counted how many times the
cost of implementation and the amount needed to finish building
the bridge Bungur.
From the analysis and comparison of the two methods are
in accordance with the parameters of existing testers it was
concluded that in order to finish building the bridge Bungur with
excavator method takes 121 days at a cost of Rp
3.287.286.91919.. While the launch of the manual method takes
139 days at a cost of Rp 3.228.751.74917.
Keywords:
Jembatan Bungur, Excavator, Peluncuran
Manual
Subject
: Jembatan
Contributor
Ir. IMAM PRAYOGO, MMT
Date Create
: 25/11/2015
Type
: Text
Format
: PDF
Language
: Indonesian
Identifier
: ITS-Undergraduate-31001150008035
Collection ID
: 31001150008035
Call Number
: RSS 624.2 Sug a
Source Undergraduate Theses of Civil Engineering RSS 624.2 Sug a, 2015
Coverage ITS Community
Rights Copyright @2015 by ITS Library. This publication is protected by copyright and per obtained from the ITS Library prior to any prohibited reproduction, storage in a re transmission in any form or by any means, electronic, mechanical, photocopying, reco For information regarding permission(s), write to ITS Library